Powercor has deployed over 200 field workers to areas affected by bushfires. Crews are focusing on rebuilding destroyed network sections and restoring power to approximately 1,280 customers.

Key restoration updates:

  • Ravenswood and Harcourt: Power restoration is anticipated today.
  • Mt Alexander Communications Tower: A specialized team has been mobilized to rebuild the power supply. Due to steep and difficult terrain, this work is expected to take multiple days.
  • Natimuk: Most customers are expected to have power restored by tomorrow.
  • Cobram: Power restoration is expected today.
  • Skipton/Streatham: Work is projected to be completed by the end of Wednesday.
  • Shelford/Meredith: The final clean-up is expected to be completed today.

A Powercor spokesperson stated that most customers are expected to have power restored by the end of Wednesday. These estimated restoration times may be subject to change based on further assessments.